Restoring spindle and controls

 

After a careful cleaning of the components, the reassembly is done with the original parts (bearings, joints, captors, etc.) while respecting the manufacturers' recommendations.
At each stage of reassembly, a test is carried out validating the function or the adjustment (concentricity, captors, preloading, etc.) and authorizing the product to progress to the next stage.

In order to guarantee the least possible level of vibration, a final balancing of the reassembled spindle is systematically carried out.

The values measured during the control process must be conform to those of a new product and are found in a report delivered with the spindle.

 
 
   
 
     